As part of Fremantle Ports' proactive Inner Harbour berth maintenance program for FY26/27, we are providing the attached preliminary maintenance schedule for your reference.
These works are necessary to maintain the ongoing safety, integrity and operational efficiency of the Inner Harbour berths.
The current planned maintenance periods are summarised below:
| Berth | Maintenance period | | Berth 2 | August – October 2026 (TBC)* | | Berth F | 24 August – 4 September 2026 | | Berth G | 09 November – 20 November 2026 | | Berth H | 08 February – 19 February 2027 | | Berth CT2 | 15 February – 19 February 2027 | | Berth CT3 | 22 February – 26 February 2027 | | Berth 1 | Late April – May 2027 (TBC)* | | | |
*Approx. 12-week interval shutdown program - Berths 1 and 2 maintenance will be undertaken through a series of planned interval shutdowns over an approximate 12-week period. Berth operations will be suspended during scheduled maintenance windows only, with operations resuming between work periods.
Please note that these dates are preliminary and may change due to operational requirements, weather, contractor availability, or other unforeseen circumstances.
The attached schedule provides an overview of the planned maintenance program and indicative shutdown periods. Further information, including confirmed timing, operational impacts and any associated restrictions, will be provided closer to each maintenance activity.
Should you have any questions regarding the program, please don't hesitate to contact customer@fremantleports.com.au.