Port of Brisbane - Operational notification #12: Port Drive Upgrade

Friday, January 20, 2017


Posted on Thursday, 19 January 2017 (Archive on Wednesday, 19 July 2017)

PBPL would like to advise that there will be out of hours' work at the following locations:

  • Kite Street from 6am to 6pm on Saturday 21 January
  • Lucinda Drive Bridge from 8am to 5pm on Saturday 21 January
  • Kite Street on Sunday 22 January from 6pm to 6am on Monday 23 January

Kite Street (Saturday)
Activities will include the construction of a pad for the crane to be used for piling. Motorists and local business will notice an increase in construction vehicles entering and exiting the site to deliver materials.

Lucinda Drive Bridge (Saturday)
A lane closure will be in place on Lucinda Drive Bridge for bridge inspection works (see Figure 1 below). Traffic control and signage will be in place to direct traffic. For the safety of motorists, stop/go traffic control may be required on Port Drive (below the bridge).

Kite Street (Sunday night)
The northbound lane approaching the Kite Street roundabout will be closed from 6pm to 6am for drainage works. Contraflow traffic control will be in place (see figure 2 below).

Delays up to 5 minutes may be expected throughout the construction site. Motorists are advised to allow extra time for their journeys.

Thank you for your patience during this work.

Should you have any queries, please contact the Port Drive Project team via email community@seymourwhyte.com.au or contact the 24hr project hotline 1800 895 929.

Figure 1: Lucinda Drive Bridge lane closure on Saturday 21 January 2017 from 8am to 5pm

Figure 2: Traffic control arrangements at Kite Street for works on Sunday 22 January from 6pm to 6am on Monday 23 January 2017